Installation of structural steel boiler Vung Ang Thermal Power Plant 1

Dated 16.05.2010, Vietnam Oil and Gas Group Corporation and Vietnam Machinery Installation (EPC) has developed installation of structural steel boiler Vung Ang Thermal Power Plant 1, milestone decision progress and success of the project and the practical activities to celebrate Party Congress parent company - Vietnam Oil and Gas Group will take place on 22 / 5 to

Boiler steel structure is steel frame size 62x61m outdoor, 74.2m high, with a system of bracing at the top with roof isolation system is located adjacent the turbine, coal bin, the central controller mind. Effective structural system crashes, support the whole entire boiler system equipment and accessories including pressure pipes, the transmission ...

Categories boiler unit, along with the turbine, cooling systems, chimney ... is one of the main items of plant. The installation of boiler steel structure to ensure the progress, quality, play an important role to decide the No. 1 unit in operation and you III/2012 units 2 operating according to your I/2013 Progress has signed the EPC contract.

Công ty Huy Hoàng Steel chuyên: Nhà kho, nhà tiền chế, Nhà thép tiền chế, Kết Cấu Thép

< Go back