PROCESS BASELINE erection STEEL BUILDING (FACTORIES, SHED), AS FOLLOWS

Refer to the basic steps for installation of pre-engineered steel buildings, warehouses, factories
PROCESS erection STEEL BUILDING (FACTORY)

1. APPLICATION PROCESS
1.1 PLANNING AND PREPARATION OF THE EVENT
- Surveying the scene, the scene.
- Make sure there is one way of moving airy and firm to the delivery truck and crane bucket can operate. Must determine the capacity of the truck and crane products are suitable.
- Survey the prevailing wind direction, thereby setting a floor plan and rallying roofing installation instructions.
- Decision of loading plans and preserve supplies. Need to pick one solid position as a place dry and gathering supplies. Supplies should be stored in areas designated for each block, and clearly marked the location of each type of storage areas (warehouses). Need to ensure that the supply schedule and preserve supplies to appropriate, nor deviation from the installation progress and considering the progress of the other subcontractors.
- To register the connection position to use electricity / water construction on the site. Should ensure a safe way to carry these supplies led to the work area.
- Check the insurance organization and the Health and Safety training for workers.
- Inspection of construction equipment, all tools, equipment, and machinery to ensure that all equipment will meet the requirements of normal work.

CHECK 1.2 LOCATION NAIL & Boulon NEO

- Before installation of steel structures, to conduct surveys and altitude reposition anchors Boulon. captain will perform this test, under the supervision of Supervision.
- The level mark must be preset based on the height of the design requirements.
- All equipment must be inspected survey accuracy.
- The intensity of the concrete foundation should reach at least 70% of design strength.
- Boulon anchor must be positioned against moving horizontally, vertically and vertically throughout the process from booking until after concreting.
- Tolerances as shown in the following table:

 
1.3 DELIVERY AT CONSTRUCTION SITE SUPPLIES


- The production department will send a notice to the Supervisor of the 24 hours prior to delivery to the loading plan year.
- There will always be accompanied by the delivery order delivered supplies, clearly stating the name of work, location, material type, quantity, delivery date, ...
- As soon as the material gathered in the yard, the inventory of supplies to match with each delivery order, and confirm the goods have been received on delivery notes. Storekeeper Supervisor will report to the school supplies list has received the status of their quality.
- Maybe unloading by hand or with a crane. With long structures, needed pole (spreader). Necessarily use nylon wire or wire cloth suitable for crane hooks course, avoid material damage. Should ensure gown cord into structures with hanging points and positioned properly, not to ruin the supplies are cranes.
- All materials must be received at the construction site Supervision inspection and observed the damage (if any). If possible, have to overcome the immediate damage, avoid construction delays.

1.4 STORAGE IN CONSTRUCTION SITE SUPPLIES

- Choose one solid area, tight and dry compaction temporary warehouse contains supplies.
- Supplies are stacked at positions corresponding to the building or area will be built, and it is next to the location that will stand crane onto a truck crane for installation. This will help the sorting and delivery is convenient during the construction process.
- Need to preserve farming structures carefully to avoid twisting torsional bent, can brace firmly in place by end 1000 mm.
- Supplies to protect them from dirt, grease, other trifles; as well as to protect not soiled water from motor vehicles on the construction site.
- Do not go back, step on materials and components.
- Complete Boulon, nuts, screws, small parts of code to be packaged and proper names.

1.5 ORDER OF INSTALLATION

• steel frame and other parts of the building can be constructed in a variety of methods, depending
some key elements are as follows:
- Type structures (such as the kind of small span, a large span, low-rise, high-rise, authoring the first beam construction, structural hollow belly etc ...)
- Type of equipment available (such as cranes, winches, lifting arms and so ..)
- Field Conditions
- The experience of the installation team
- The conditions of each separate job
• Sequence / construction methods must be studied and planned, so that construction can proceed safely, economically and efficiently.
• Process specific construction methods for each project must be discussed in advance between the commanders of the building and construction captain, showing details of the request on the records and signed certification exam before deployment drain.
* There are several common construction method has been confirmed over time. Here are some typical application guidelines for a menu and works with middle column

STEP 1: INSTALLATION COLUMN HARD TIME KEY
1. Installation 4 column border, and 2 middle column, 2 & 3 axis
- Using the crane 20 tons, with a minimum length of 12m arm.
- Use straps tie around the top end of the column code

 
2. Aligning the vertical, position, altitude
- Set construction scaffolding in each column
- Tighten the hard just Boulon anchor, wedge plinth as required
- Equipment: double bottom, Theodolite and Roulettes
- Tighten all anchor Boulon with a wrench to tighten a moderate force
3. Installation of all wood beam walls between the columns and tighten Boulon
- Lifting equipment purlins: ropes with hooks secure key
- Equipment screw: spanner tubes, moderate tightening force
4. Replace the temporary bracing in 2 sides of each column
- Using a 12mm cable, one end attached to the outer side of the column below the first code column
- Top of the remaining cables connected to the connector terminal V 2 iron bowl anchor together Boulon

 STEP 2: INSTALLATION OF BEAMS FIRST AGREEMENT
1. Combination RF1-1 & RF1-2 connecting beams on the ground
- Use straps tie around structures in two points from the tip structures around a quarter length, side dishes purlins
However, the cantilever outside hanging points to calculate accurate water to avoid twisting components of the load itself. Aviation segment than 1/3 length bar structures. Elevation angle should be calculated by avoiding twisting forces along the crane. For safety, it is recommended to use more than 2 points tie belt crane
- Equipment Crane: Crane 20 tonnes required minimum length of 12m
- When the combination, use the 50mm thick wooden bar to support Statistics structures
- Equipment intense Boulon screw: spanner force (torque wrench), its minimal tightening torque according to the proposal (see table tightening Force Moment)
- Getting temporary bracing and purlins on beams brace truss
- Use sandpaper and cloth to clean the components. Mending and scratched paint roller painting, with the right stripe coating system used.
2. Insert 1 selling truss up column
- Use straps tie around in the second component from the tip selling point truss about 4m, the outermost edge purlins bowl
- Use a 20-ton truck crane

 
- Crane sold the first contract put into place a pillow on top of two columns in a row, holding steady with crane
- Workers will manipulate standing on scaffolding, sliding and screw flange Boulon truss columns and beams connected to a state close enough
- Use of temporary bracing wire truss beams spaced about 6m hold this first lease sale held in the Boulon plinth with iron bowl V
- Release the wire lightweight truss crane may try to sell stable before releasing the crane must wire.
3. Repeat steps 1 & 2 for the sale of the remaining truss, truss beams forming complete

 
STEP 3: INSTALLATION OF BEAMS SECOND AGREEMENT
1. Do the same {2} for the second step of the frame truss girder truss sell second
• Only use temporary bracing wire of 2 side in the middle of each sale contract, pulling on the Boulon plinth with iron bowl V
2. Installation of a rhythm from the top down to the wood beam rafter tails to keep the sale agreement in place.
• Use a rope to the hook with safety lock to pull the roof purlins craft
• Equipment Boulon purlins M12 screw: spanner, tubes, normal tightening force

 STEP 4: TIME COURSE COMPLETION 100%
1. Installation of the entire truss bracing, purlins, anti-purlins - 100% of the
2. Installation of the entire cross-bracing cable eternity truss columns and beams for key space.
3. To all this tension in the liquid state (not a stretch)
4. Align the rafter beams
- The measurement points are associated ciphertext. Allowed tolerance of displacement between points is 1/500
- Use of temporary bracing to calibration frame
- Tighten fully the eternal tension.
- Signing inspection records through time courses


 

STEP 5: INSTALLING THE FRAMEWORK AGREEMENT AND ENTIRE purlins
1. Installation of the column and the column boundary between the axes 4,5,6,7,8,9
- Use a 20-ton truck crane
- Use straps (40 tons / 9m) tie around the top end of the column code
2. Adjust the vertical position and height of the column
3. Do the same [step 3] and [Step 4] for all truss girders and roof purlins
+ For the structure has a column in the middle, not allowed laying out a lease seller and the seller to the remaining lease. Doing so will change the design calculations diagram of the frame, causing imbalance in the frame, which can lead to put down work when experiencing bad weather.


 
STEP 6: INSTALLATION AGREEMENT FIRST RECOVERY
1. Installation of the column and the column boundary between the shaft 1
2. Aligning the vertical, position, altitude
3. Screw the entire anchor Boulon.
4. Installation of the first gable truss beams on the gable column
- Use the top rope with a hook with safety lock to pull the roof purlins craft
- Equipment Boulon purlins M12 screw: spanner tubes, normal tightening force
- Release the wire lightweight crane girder truss structures try even out, prior to release the crane
5. Repeat step 4 for the remaining truss girder structures, truss beams forming the gable

STEP 7: COMPLETE INSTALLATION AND AGAINST 100% purlins purlins
1. Installation of the entire truss bracing, purlins, purlins combat for the first time hoi- 2 100% of
- Using the crane lifting the abdominal brace truss girder (strut) to the roof.
- Use the top rope with a hook with safety lock to pull the roof purlins craft
- Equipment Boulon purlins M12 screw: spanner tubes, normal tightening force
2. Install cross bracing eternal entire columns and beams of truss for key space.
3. To all this tension in the liquid state (not a stretch)
4. Align the rafter beams
5. Tighten completely the permanent bracing.
6. Remove all temporary bracing of the building.
7. Check and verify all connections, make sure all are equipped Boulon. All high-intensity Boulon (Boulon texture) must be tightened to the tension as required.
8. Check the entire structural frame last time: the correct degree azimuth and vertical ground
STEP 8: PULL UP ROOFING ROOFING ROOF
- Place each sheet roofing on the tube slide, thanks to clinch 6mm keep sliding on the cables.
- Each worker standing in each tube truss would anchor on a rope pull slide tube run
to bring sheets and corrugated iron roofs.
- After up to truss roofing, used manually moved into place on the roof purlins.
- When pulling enough roofing for the first time, organizations will begin installing roofing work.

 


STEP 9: ROOFING ROOFING
1. Installation of the cable system on the roof safety
2. Prepare the electric system construction
- Electric wires and the cabinets against shock breaker (ELCB) must be taken to the roof in a secure eligibility. The system must be high off the ground combat.
- Electric wires should drain into the tube anchor location, avoiding direct exposure to the corrugated roof and roof purlins.
- Connect the two power cables with 3-pin socket on the circuit breaker cabinet against shocks, pull to the installation location in preparation to use.
3. Preparation of construction scaffolding system
- Must be inserted at least one climb the scaffolding at the terminal roof salmon, served up / down daily roof
4. Installation of the first corrugated iron sheets
- Position the first plate, soup to give an edge gutter lú in uniform.
- Installation of corrugated roofing.
- Check regularly to the plate has been aligned under the edge of roof gutters.
- If the gap from the last plate on the wall materials or facades gable buildings hip width that is less than half the plate, can cover or capping by flashing. In this case, all the positive waves must be tightly covered and arrested,
STEP 10: INSTALLATION purlins WALL - WALL TON - gutters - downspouts AND ACCESSORIES
1. Prepare construction scaffolding system
- Construction scaffolding system must be arranged outside a side wall of an approximately 300mm purlins. All supplies will be passed on in accordance with this 300mm space.
- Can allow corrugated walls constructed using the rope ladder has passed safety tests on the links fixed location.
- Workers will hook directly into the waistband safety scaffolding or ladder system.
2. Installation of the entire walled purlins, purlins fight between the columns frame
- Lifting equipment purlins: ropes with hooks secure key
- Equipment screw: spanner tubes, moderate tightening force
3. Installation of the entire corrugated wall
- Pull corrugated wall with rope tied to religion
- Cases against shock breaker (ELCB) located near the ground
4. Install gutters, ventilation leaves, etc .. fringing
- Equipment fitting: screw gun.

1.7 APPLICATION EQUIPMENT
1. Equipment mobile machinery
Mobile machinery including delivery trucks, tank truck crane, hoists etc ...
Only allow the mobile equipment has passed inspection skilled worker control on construction sites.
At-risk place mobile machinery can come into contact with electricity, all electrical wires must be fenced or signal flags. These wires are at risk of causing accidents must be a power interruption, or make safe before starting any work went public.
Not to have machinery that operates on electrical wires.
Never operate machinery lies mains voltage> 220 Volt a less than 4.5m. Just being there is only one nominee for the prime performance machine operator, except emergency stop signaling.
Avoid traveling near or just below 1 len.Tat both objects being crane hoisting loads are wired up to soups (tag line) to drive things.
Before hoisting anything, must clearly identify the standing position of the crane and the crane down of positions in the construction area. The work must be carried out to ensure occupational safety and risk analysis can be (based on the Health and Safety in the installation process at the site).
Before hoisting plants, cranes should be positioned and the crane folded hands to push the water out. Arm length, angle required, radius of hot and safe lifting load must be estimated based on the schema Hoisting manufacturers.
In every stage of construction, probably to avoid or minimize the damage portion of the material of paint finishing, using wire or belt nylon cape with protective buffers in places exposed to the metal structures ; or by using a regular pierced holes Boulon shackles to lift.
2. Wire cranes and slings required:
Should definitely check carefully the crane and sling cables required. The cables and wires hanging damaged must be removed and destroyed immediately.
When conducting cranes, crane avoid arbitrary strings. Need protected by wire cranes lining the seat angles. Absolutely no sudden shock when the crane, because the sudden shock loads will increase 3 times normal, dangerous for hoisting rope. When not in use, it should be neat trough crane wire. Never let wire crane overload.
3. Seamless Education Execution
Must use planning as well as construction scaffolding installed so as not to obstruct the movement of the crane arm and about themselves, nor make it difficult for construction operations.
Always scaffolding Statistics on hard ground or right seat plank, minimum size 200 x 200 mm. The scaffolding had been arrested separately Statistics tight security on fixed structures with a minimum of 1.5 m of space. Each floor scaffolding to hold above the floor under the wire or pipe scaffolding, so that to ensure safety.
4. Hand tools:
All hand tools must have a strap that held against falling
To use the device for the right purpose. Never use a portable device for jobs outside the intended purpose. Never use the temporary replacement equipment.
Certainly never use the tool was broken, machinery and equipment which windings frayed or erroneous or without shooting guard.
Must shutdown and isolated from the power source, and special warnings when carrying out cleaning and adjustment.
Have guessed that the machines will not operate before removing the protective shutter for repairs or adjustments.
To report on all the machines damaged paint, breakage ... for the captain.
5. Cutting with welding flame:
Only skilled workers, are adequately trained and have the new guidelines are allowed to use the oxygen equipment, gas, welding equipment. Monitoring Health and Safety Project required to conduct initial inspection and save the report before allowing use.
All scuba browser must be stamped and approved for use. The compressed gas cylinders should be porters careful, avoid collisions, bumped or dropped. Must always preserve this bottle in an upright position.
The compressed gas cylinders should be moved by trolley, not rolling. When hoisting cages or crates used to hold, never use a lifting magnet.
On pneumatic cylinders have safety cap when not in use and when being transported.
There should be safeguards against fire backwards by the instruments already adopted, to avoid the fire from spreading to the system of gas cylinders.
Wind is not rock torch water hammer to knock slag used as welding or soldering flakes.
Before conducting burning, welding or heating, workers are responsible for checking the other side or the bottom of the object to be sure that all danger from fire or damage have been excluded. Fire extinguisher must be available properly.
Never been heating an object lying flat on the concrete floor. Should ensure that there is an air gap between the material and the concrete if the concrete will not crack if the temperature is too high.
Not to torch the wind kicks in a closed jar or container. Leaks can be the beginning of a disastrous explosion.
Before leaving the workplace, to turn off gas valve on the tube by the lead and followed by van on the torch. Need guess no gas leaks.
Conduct regular inspection of the entire field of welding, air ducts, air pressure meter and other combustion devices,